Late start date (LS)

In the critical path method, the latest possible point in time that a schedule activity may begin based upon the schedule network logic, the project completion date, and any constraints assigned to the schedule activities without violating a schedule constraint or delaying the project completion date. The late start dates are determined during the backward pass calculation of the project schedule network.

This is auto-generated content. You can help to improve it.
0
Collect to Blossary

Member comments

You have to log in to post to discussions.

Terms in the News

Featured Terms

Harry8L
  • 0

    Terms

  • 0

    Blossaries

  • 1

    Followers

Industry/Domain: Holiday Category: Festivals

Dragon Boat Festival

Celebrated in China, as well as other Southeast Asian countries, Dragon Boat Festival is on the fifth day of the fifth month of the lunar calendar. On ...

Contributor

Featured blossaries

Gemstones

Category: Other   1 20 Terms

Popular African Musicians

Category: Arts   1 15 Terms